Case Study: Boosting Efficiency in a Newly Constructed Building in Zürich

Here is how ECCO2's expertise in Monitoring, Optimisation, and Performance Gap Solutions helped this building perform at its best.

Case Study: Boosting Efficiency in a Newly Constructed Building in Zürich

How ECCO2's expertise in monitoring, optimisation, and resolving performance gaps helped this building.

✅ Result: 40% reduction in electricity consumption.

✅ Result: Resolved remotely in just 5 minutes.

  • Planned requirement: 22 kWh/(m²*a)
  • Actual consumption: ~27 kWh/(m²*a)
  • After optimisation: ~23 kWh/(m²*a)